A recent decision by the Environment and Planning Review Tribunal has overturned a Planning Authority decision, ordering it to approve a permit for the extension of a restaurant, the installation of light and increasing the number of tables and chairs in an EU Natura 2000 site in Dwejra.

Without any doubt, this throws a lot of light on the official political disrespect, disinterest, exploitation and disregard for the environment as well as national and international legislation.

Dwejra is a Special Protection Area and a Special Area of Conservation with regard to biodiversity, in line with the Birds and Habitat Directives. It is part of the EU Natura 2000 network because of its importance to the EU.

The Malta Environment and Resources Authority is the responsible competent authority recognised by the EU. Competent national authorities are those entitled to give authorisation or consent to a plan or project in Natura 2000 sites.

 

Dwejra is the best remaining site on the islands for astronomical observations. Photo provided by the Physics Department and the Institute for Astronomy and Space Sciences

Dwejra is also designated as a ‘dark sky heritage area’ in the Gozo and Comino Local Plan.

Article 6 of the EU Habitat Directive can be regarded as a key framework for giving effect to the principle of integration with regard to the management of the protected areas in a sustainable way and sets the limits of activities that can impact negatively on protected areas.

In an international context, Article 6 also helps to achieve the aims of relevant international nature conservation conventions such as the Berne Convention and the Biodiversity Convention (Malta is a party to both), while at the same time creating a more detailed framework for site conservation and protection than these conventions themselves do.

Where assessment is required by Article 6 (3) it takes the form of an assessment under Directive 85/337/EEC (on the assessment of the effects of certain public and private projects on the environment), where public consultation is necessary.

In this context, it is worth mentioning the possible longer-term implications of the Aarhus Convention, which emphasises the importance of public consultation in relation to environmental decision-making.

According to Habitat Directive’s article 6 (2) “any plan or project not directly connected with or necessary to the management of the site but likely to have a significant effect thereon, either individually or in combination with other plans or projects, shall be subject to appropriate assessment of its implications for the site in view of the site’s conservation objectives”.

The Environment and Planning Review Tribunal has completely undermined Malta’s obligations at EU level

“In the light of the conclusions of the assessment of the implications for the site and subject to the provisions of the Habitat Directive (para 4), the competent national authorities shall agree to the plan or project only after having ascertained that it will not adversely affect the integrity of the site concerned and, if appropriate, after having obtained the opinion of the general public.”

An EU Commission publication dated 2000, Managing Natura 2000 Sites – The provisions of Article 6 of the Habitats Directive 92/43/CEE, explains that “member states shall take appropriate steps to avoid, in the special areas of conservation, (like Dwejra) the deterioration of natural habitats and the habitats of species as well as disturbances of the species for which the areas have been designated, in so far as such disturbance could be significant in relation to the objectives of this directive”.

The article also states that “member states shall take appropriate steps to avoid, in the special areas of conservation, the deterioration… as well as disturbances…” of species and habitats for which the sites have been designated and should also be implemented if necessary outside the sites. (Article 6 (2)).

Disturbances include, among others, noise and source of light.

The intensity, duration and frequency of repetition of disturbance are, therefore, important parameters and can be regarded as a significant disturbance.

Even a plan or project that includes conservation management among its objectives may still require assessment.

Although the management plan for Dwejra has long been drawn up with the help of EU funds, and approved by the EU, it is still gathering dust on the ministry’s bookshelf.

There is still no administrative set-up for its implementation, enforcement, management, administration, education and no stakeholders are involved, as obliged by the management plan.

The Environment and Planning Review Tribunal has completely undermined Malta’s obligations at EU level. Can the ERA contest such a decision in court, especially when the Minister for the Environment has publicly stated that he does not agree with this permit? If not, does this decision mean the ERA is impotent as a competent authority responsible for EU obligations when confronted by such a tribunal?

Do the citizens have to refer the matter to the EU to achieve what the ERA should be on the front line defending on their behalf?

This is definitely another decision reached by hand-picked political academics,whose short-sighted decision embarrassed Malta with regard to its international obligations.

If such a tribunal is independent, then the responsibility has to be carried by those people involved in such a decision and who have completely ignored and defied the decision made by two national competent authorities and also the public with great political and environmental consequences.

It is high time the EU DG Environment investigates how Natura 2000 sites in Malta are being brought to disrepute.

aebaldacchino@gmail.com

alfredbaldacchino.wordpress.com

Alfred Baldacchino is a former assistant director of the Malta Environment and Planning Authority’s environment directorate.

related articles:

Dwejra: Gone with the wind

A window pain for sure

Sifting solidified sand at Dwejra

 

aebaldacchino@gmail.com

alfredbaldacchino.wordpress.com

Advertisements

EU funds endanger Buskett N2K site

May 13, 2017

Saturday, 13th May, 2017

Endangering Buskett 
Alfred E. Baldacchino

Buskett is a Tree Protection Area, with some trees protected for their antiquity, a scheduled woodland, an Area of Ecological Importance, a Site of Scientific Importance, a Site of European Importance, a Special Area of Conservation, a Bird Protection Area, and above all an EU Natura 2000 site.

The remains of an Ash Tree, after being handled by a Landscaper, in the Natura 2000 Buskett.

Yet, to date Buskett has never been professionally managed, especially on the lines of EU obligations. Never. There is absolutely no will, no vision, and no professional commitment. To the extent that a past environment minister was made to believe that Buskett is a garden. There were plans to transform this important ecological habitat into a ‘quality garden’ on the lines eventually implemented at the Mdina Ditch.

One would have thought that this was just a political flash in the pan by a gullible politician who was taken in by those with commercial interests. But to this day, professional environmental responsibilities still have not reached the level of Cabinet’s political acumen.

The only type of management approved by the Authority for the Protection of the Environment is the chopping down of protected trees, such as this one in Buskett – A Natura 2000 site.

As an EU member, Malta had to have management plans implemented for all Natura 2000 sites by six years after accession. This deadline was not met.

Following public consultations, later approved by the government, and boasted about by the incumbent Minister for the Environment, management plans are not yet implemented, and it seems they will never be.

A recent visit to Buskett revealed the complete political failure, lack of professionalism and irresponsibility with regards to the management of this important EU Natura 2000 site.

Clearance of important natural habitat in a Natura 2000 site to restore of a rubble wall.

An extensive area of maquis was recklessly bulldozed and obliterated to enable the restoration of a rubble wall. While the restoration of rubble walls is necessary, and those in hand are being professionally built, this can never justify the massacre of flora and fauna: habitat and species of European importance.

The rich maquis habitat as it was before it was bulldozed with the blessing of the Ministry for the Environment.

I wandered around Buskett and I could see piles of earth and stones dumped on sensitive habitats: habitats important for rare and endangered species, all listed in the data sheets sent to the EU to justify the importance of such a Special Area of Conservation of European Interest.

A butchered Ash Tree where, a couple of weeks before, I was photographing its new seeds.

Piles of stones and earth dumped on sensitive habitat in this EU Natura 2000 site.

It is heartbreaking to see two protected and rare hawthorn trees that were chopped from ground level to make way for machinery, earth and stone dumping. A rare protected ash tree was heavily butchered.

Unfortunately European Union funds are being mismanaged, endangering an important sensitive habitat which according to EU legislation, the Minister for the Environment is obliged to protect on behalf of Malta and the EU.

According to the EU Habitats Directive (article 6.3), an appropriate assessment has to be drawn up for any plan or project not directly connected with, or necessary to the management of a Natura 2000 site, but which is likely to have a significant effect thereon, either individually or in combination with other plans or projects. Such an appropriate assessment is needed to highlight the implications for the site in view of its conservation objective.

The national competent authority for the EU Habitats Directive (the Environment and Resource Authority – ERA) shall eventually endorse the plan or project only after having ascertained that the conclusions of such assessment regarding the implications for the SAC will not adversely affect the integrity of the SAC concerned. ERA is also obliged, if appropriate, to obtain the opinion of the general public.

Two mature protected hawthorn trees in this Natura 2000 site, 2.5 metres high, were raised to the ground seemingly by the approval of the Ministry for the Environment and ERA 

Can the minister publish the appropriate assessment made (naturally if it has been done), which enabled the ERA board to approve such works in this important Natura 2000 site?

If not available, then ERA approved such works blindfolded, which is very irresponsible, or else the ministry is in complete darkness of its responsibility, and its personnel is on a wild unmonitored spree to obliterate a delicate natural habitat just to restore a rubble wall. Ironically, posters at Buskett advertise these works as an EU-funded Life Saving Project.

It seems that following the acquiring of EU funds, the most important thing is to nail a poster acknowledging EU. How these funds are spent, and whether they are in line with the obligations of the EU Environment Acquis, is not important, not even to the Ministry.

Considering the fact that the minister’s Environment and Resource Authority board is made up of the cream of the crop of Maltese academics, such officially approved ecological damage with EU funds is worse than one can image, both from a professional, an administrative and a political point of view.

60 mature olive trees were chopped down by the approval and financing of the University of Malta, following populist demands. So if it can be done on the University campus, why not on public land?

It reminds me of the massacre of 60 established olive trees on the university campus, where no one batted an eye. We now have to suffer this ecological destruction in a Special Area of Conservation of national and European importance. Seems that academic qualifications today at best are of secondary importance when one sits on a political board.

Have we reached a stage where the destruction of the environment and the ecosystem has achieved virtual academic qualifications, approved not only by politicians but also by the top academic institution of this unfortunate country that seems to sit and tacitly approve?

This is a glaring declaration of total failure of the ministry’s obligations with regards to the protection of the environment. It seems that the latest environment ministers, one from either side of the local political hegemony, are competing among themselves as to who is the most committed to the destruction of biodiversity.

It would do no harm to remind, once again, the environmental promise contained in the 2013 electoral manifesto:

“The Environment and Resources Authority… will focus more specifically on the conservation, protection and amelioration of the environment and resources while undertaking also the responsibility of the important role of an environmental regulator, which presently our country does not have.”

A visit to Buskett where this EU Natura 2000 site is being endangered by EU funds, shows not only how an environmental regulator did never exist in the past, but also how the present one is working diametrically opposite to what has been promised and contrary to national and international obligations. Not only is it not functioning, but it is officially involved in such ecological damage.

Have we reached a stage where the destruction of the environment and the ecosystem has achieved virtual academic qualifications?

The minister has gone on record as saying that he has a “sound environmental policy”. Buskett Natura 2000 site, shows the lack of a will to protect biodiversity, as promised, all the result of such a “sound environmental policy”.

 

The result of the ‘sound environmental policy’ with which some are very proud.  Seeing all the above official ecological damage, this is the best diplomacy I could manage. And I am sure there are many others who feel the way I do.

Alfred Baldacchino is a former assistant director of the Malta Environment and Planning Authority’s environment directorate.

aebaldacchino@gmail.com

see also:

https://alfredbaldacchino.wordpress.com/2016/09/15/another-buskett-onslaught/

https://alfredbaldacchino.wordpress.com/2010/06/21/buskett-%e2%80%93-a-special-area-of-conservation-in-the-eu/

https://alfredbaldacchino.wordpress.com/2010/01/26/il-buskett/

https://alfredbaldacchino.wordpress.com/2016/05/09/trees-butchered-at-university/

https://alfredbaldacchino.wordpress.com/2014/04/02/a-cash-cow-in-the-ditch/

https://alfredbaldacchino.wordpress.com/2013/03/07/the-garden-at-mdina-ditch-officially-inaugurated/

https://alfredbaldacchino.wordpress.com/2012/09/28/qerda-tal-biodiversita-fil-foss-tal-imdina-biex-isir-gnien-ta-kwalita/