Environment hit by EU funds

July 27, 2019

Saturday, 27th July, 2019

Alfred E Baldacchino

On July 18, the Planning Authority approved the Attard Central Link Project for which the EU is going to contribute €55 million.

There were a lot of questions and doubts on this project which everybody hoped a meeting would iron out. Not only were these not answered but even more doubts were cast.

The meeting was opened by the Infrastructure Malta CEO, Engineer Fredrick Azzopardi, representing the Ministry for Transport and Infrastructure. He tried to convince those present that this Central Link project has many benefits. Stakeholders subsequently expressed more doubts and asked more questions, confirming the lack of public consultations.

Here is a résumé of the questions:

Those present for the meeting asked how such a project would be beneficial for full-time or part-time farmers, and those involved in animal husbandry.

There were also questions about the loss of 22,000 square metres of agricultural land and the subsequent loss of jobs due to this land being destroyed.

There were concerns about the fruit and crops in the area since these would be covered with additional emissions that would disperse across the adjacent fields.

The biodiversity of the area was also a point of concern seeing as this was facing the destruction of more than 550 trees, many of which are protected, and the loss of their contribution to climate change and the ecological niches of which they form part.

Questions were asked about the hydrological system feeding Wied is-Sewda, along with the farmers’ cisterns and the disruption of natural water flow destroyed by the project (which was unbelievably referred to as “flood water”).

Not to mention the concerns about the psychological and physical health of residents in the vicinity and beyond Attard, including those residing in Siġġiewi and Qormi, given the increase in noise pollution and toxic chemicals that the project is sure to cause.

There was also the question about the cultural heritage of the area and the number of historical constructions that would be threatened, some dating back to the times of the Knights of Malta.

Will the towers being built close to the Malta Financial Services Authority, nonchalantly approved by the lack-of-vision, commercially minded PA – definitely be­yond the carrying capacity of the area – be the main beneficiaries of the public land being taken up and the EU funds being spent?

None of the social and environmental elements mentioned above is going to bene­fit from this EU-funded project.

None of the questions were answered by the CEO of Infrastructure Malta. None of the concerns put forward were even addressed. The Environment Im­pact Assessment presented gave a very superficial indication of the project’s negative impacts.

The chairman of the Environment and Resources Authority, as silent as a grave, in a later interview in the press (July 19) was quoted as saying that “he had nothing to add” because none of the comments raised by stakeholders during the meeting changed anything from the ERA’s report.

He called most interventions against the project “emotional”! He also justified the project “on the basis of national interest”.

In yet another section of the press (July 19), Environment Minister José Herrera said that “the authority (ERA) would be vigilant and in a consistent way, [fulfil] its duties to offer the greatest elements of protection to our natural capital, and this with the means and parameters established by law”.

This trophy was first awarded to MEPA in 2015. Despite the fact that the year 2019 is not yet out, this has been awarded to the Planning Authority and the Infrastructure Malta for the environmental devastation that they are involved in.

 

So long as there are EU funds, then they have to be spent irrespective of the foreseen environmental destruction

The Infrastructure Malta CEO said that this project, according to his economist’s report, will “give back” €16 savings for every €1 spent without even saying how. His economist did not refer to any externalities or the hidden costs that would be borne by the public and the environment. No wonder all the above questions asked were ignored by the CEO.

With regard to the uprooting of trees, he told the press, with hand on heart, “they are using the ERA compensation system of planting trees for those uprooted”, and that the “trees to be planted as compensation will have to be at least three metres tall”. This implies they will all be imported irrespective of the possible dangers of diseases and other invasive species they may bring with them, contrary to EU recommendations as administered by ERA.

Farmers were up in arms when they heard the Infrastructure Malta CEO say that they had been consulted, and could not keep from emphasising that this was a blatant lie.

This is how decisions are taken in Malta – a final late meeting on decision day without the stakeholders being properly consulted, despite this being a requirement whenever EU funds are involved.

All stakeholders and the public have to be involved and consulted so that they are part of the decision rather than just being informed of the decision after it has been taken. Consultation does not mean planting political individuals amidst the public and stakeholders and having them clap every time their minister’s wishes are supported.

The bottleneck at the roundabout beneath Saqqajja Hill will not only remain as it is but will become worse because of the heavier and faster volume of traffic that will be introduced, as advertised by the Ministry’s billboard in Attard.

How on earth can one imagine that the bulk of this traffic has to make its way up Saqqajja Hill where there are only two carriageways? No explanation whatsoever was given by the Infrastructure engineer.

Unbelievably, the EU is dishing out €55 million to the Ministry for Transport and Infrastructure for this particular project, while stakeholders and the public have to depend on voluntary contributions to protect the country from environmental and social destruction.

If there were no EU funds, there would not be such useless environmental destruction taking place. The impression one gets is that, so long as there are EU funds, then they have to be spent irrespective of the foreseen environmental destruction.

ERA, the competent authority recognised by the EU for the protection of the environment, gave its endorsement of this environmental destruction because most of the questions asked, according to the ERA chairman, were “emotional”.

On its website, the ERA says that it is committed “to safeguard the environment for a sustainable quality of life”. There was no confirmation of this whatsoever from the ERA chairman during the meeting, which took place on a very black Thursday for the Maltese environment, with the blessing of ERA.

Can anybody with a real national, social and environmental conscience, and without any political influence, be blamed for losing all confidence in ERA?

aebaldacchino@gmail.com 

Advertisements

To Gozo with love

January 8, 2019

Tuesday, January 8, 2019

Alfred E. Baldacchino

The proposed Gozo tunnel has resurfaced once again. No surprise. The MEP elections are round the corner. It is normal that white elephants are driven in the political arena during such times.

Their main aim is to try to get on board the blindfolded followers who can be convinced that a circle is square, especially if this comes from the political leaders, no matter from which side.

This time a new step in this regard has been made. An international call for tenders for the construction of the 10 km underwater tunnel, plus additional inland excavation – approximately an additional 5 km – was announced.

The information was revealed by the Minister for Transport, who regrettably, is already associated with the destruction of any tree which dares stand in the way of spending EU millions to widen roads – the latest to bite the dust are national trees at Buqana.

Suggested socially and environmentally friendly alternative connections between the two islands.

Does the public have a right to know what were the findings of the social, environmental and financial impacts of this tunnel? After all, our country belongs to all of us and not just to politicians and entrepreneurs.

Has consideration been given to the negative impacts of such works on the only remaining unadulterated water catchment area at l-Imbordin?  How will this affect the water table? And how will this affect the livelihood of  those involved in agriculture in the area?

What about the Gozitan farmers on the other side of the tunnel exit? Is this of importance? Who will benefit most from the tunnel, the people or the capitalists? Have such studies been undertaken despite the official tender calls? Has the general public a right to know of these negative impacts or are these confidential too? Would any professional firm tender for such works without such important scientific studies?

How much deeper under the 35 m of sea-depth will the tunnel be excavated? What kind of geological strata grace such depths? What is the position of the ERA?

Who will be giving the assurance and take responsibility for any loss of human life and limb in meddling with such dangerous large and deep sea bottom faults the area is full of, as has been pointed out by geologist Peter Gatt?

Will the responsible minister and the Planning Authority, which incidentally is in his portfolio, be shouldering all responsibility for loss of human life and ecological and social destruction and disasters, both on the site in question and also, directly or indirectly, in the affected areas? Somebody has to.

The answer to these and other questions raised by sociologist Godfrey Baldacchino ‘What purpose should tunnel serve?’ (January 4) have never been addressed, much more answered.

In the background of this political circus, one can hear the artificial, shameless pleadings that this is all in the interest of the general public, especially Gozitans, who deserve to have better crossing facilities between the two islands. No doubt about it.

Everybody agrees that Gozitans and Maltese deserve better crossing facilities. But not with such destructive decisions bereft of any technical and scientific studies, solely based on local arbitrary political acumen and agendas.

There is an ever-increasing momentum among the public, not least Gozitans, that the best environmental, social and financially friendly approach is the fast ferry service between the two islands. These can run not just from Mġarr to Ċirkewwa, but also to St Paul’s Bay or Qawra, to Sliema and also to Valletta.

And if found that there is the appropriate economically feasible demand, also to the Birżebbuġa and Marsaxlokk.

This would help commuters from getting caught in traffic jams along the way in St Paul’s Bay, Mosta, Birkirkara, Msida, Ħamrun, Floriana or everywhere along their journey across the island, something the tunnel can never achieve. The sea routes are already available at no cost at all. And these do not need any widening.

Who will benefit most from the tunnel, the people or the capitalists?

If the Ministry of Transport is open to suggestions, unless they believe that the people out there can all be convinced that a circle is square, they can plan a holistically better managed public transport system on both islands, in connection with the stops of these fast ferries service. The present service between the two islands should also form part of this national transport management plan.

Such holistic public transport management can include, among others, a shuttle service from the Valletta ferry stop to the Valletta bus terminus to cut down on private transport and help commuters reach their destination easier.

Another shuttle service can take commuters to the Blata l-Bajda park-and-ride to reach a parked car which, if one wishes, can be left there. Such facilities can also be available at every fast-ferry stop.

This would be far less expensive and more socially and environmentally friendly than the proposed tunnel, in all aspects. It would also help commuters to cut down on expenses, both in the consumption of petrol, and also in the wear and tear of their cars. It would also help to further reduce pollution from the urban and rural environment, with all its negative impacts on the people’s physical and psychological health.

Furthermore this would also help to lessen the stress in crossing from one island to the other, especially through the 15 km+ tunnel, where all the psychological impact studies seem to have been completely ignored. Unless of course these negative social impacts are also officially regarded as further contributing to the economy.

It would also be interesting to know the toll commuters will have to pay to use the tunnel. It seems that this is not in the public interest either, possibly because it might scare some of the ‘faithful’ who may have concluded that driving through the tunnel would be free, like driving through any other road.

From past experience, I am convinced that the minister responsible for transport has a positive environmental awareness and would positively study any alternative suggestions. However, I have my doubts how much power he has to decide himself because of directions from upstairs.

From the way the social and environmental fabric of these islands is being officially exploited and destroyed, without any scientific studies or regard for their negative impacts, it is very difficult not to conclude that their destruction is part of an official political agenda supported by the square-circled mentality, and endorsed by some academics paid to decide politically and not to think professionally.

The Minister for Transport, nonetheless, is both personally and collectively responsible for the future sanity and well-being of the people of these islands and their environment with regards to the tunnel and transport management.

The crossing to Gozo and back can be made easier for the benefit of the people of these islands, with love and not with co-ordinated politically motivated destruction.

aebaldacchino@gmail.com

Alfred Baldacchino is a former assistant director of the Malta Environment and Planning Authority’s environment directorate.

This is a Times of Malta print opinion piece

other related articles:

Tunnelling the cross

Efficient link to Gozo

 

 


Glyphosate & you

January 16, 2017

times of malta

‘EU’s permission to ban glyphosate is not needed’

Monday, January 16, 2017

 Sarah Carabott

 

photo-pesticides

Placing peticides on the market is the role of the member states. Photo: Shutterstock

Malta can still decide to ban products containing the weedkiller glyphosate and does not need any EU permission, environmentalist Alfred Baldacchino insists.

Mr Baldacchino, a former assistant director of the environment directorate at the Malta Environment and Planning Authority, was contacted after this newspaper was informed the government would only ban the use of glyphosate when such a move was ordered by the EU.

Only last summer, the Environment Ministry said the government had started the process to ban glyphosate. However, only products containing both the active substance glyphosate and the co-formulant POE-tallowamine are being banned. This, according to the ministry, includes Hopper Blu, Roundup, Roundup Max and Seccherba Respect.

stephanie-seneff-glyphosate

The price society pays to have ‘cheap’ food. Is it worth it?

A study has just been released showing that Roundup caused liver disease in rats. The World Health Organisation’s cancer agency says glyphosate itself is a “probable carcinogen”. Mr Baldacchino said the government was right to vote last June against the use of glyphosate in line with the precautionary principle cited by environmental groups, which stated that potentially hazardous substances should not be used unless they were proven to be safe.

What more proof does the minister need? The minister should seek the advice of all stakeholders, not just commercial ones

“But it seems the Environment Minister’s spokeswoman wants the minister to run with the hares and hunt with the hounds.” “The EU does not authorise the placing on the market of pesticides. It is the role and responsibility of the member states to do so and the regulator in this area is the Malta Competition and Consumer Affairs Authority.”

“Malta can still decide to ban products containing glyphosate if it is not sure that the chemicals can have negative health and ecological impacts,” he insisted. Mr Baldacchino noted that it had already been proven that glyphosate killed bees, directly when they came in contact with the product and also by killing the flowers they fed on. Traces of the chemical had also been found in honey.

dead bee 16“What more proof does the minister need? The minister should seek the advice of all stakeholders, not just commercial ones, and this includes NGOs, technical experts, health experts, environmentalists and beekeepers,” he said.

The ministry, Mr Baldacchino continued, should also make clear what its intentions were and how it would enforce the ban. He wondered who would monitor what chemicals were used in herbicides and pesticides.

In a letter sent to the Environment Minister, the Clean Food Movement expressed dismay at the ministry’s watered-down position, saying the ban had turned out to be “no more than window dressing”.

“We are now more concerned than ever about the possible continued use of glyphosate on these islands,” the letter to the minister read.

Contacted in his capacity as chemical expert, Alfred Vella, the University rector, said herbicides containing more than one active ingredient did exist. POE-tallowamine was frequently present in herbicide compositions to serve as a “surfactant”, which was not designed to kill weeds but to make the delivery of the actual toxic chemical, such as glyphosate, more effective in its action. Still, at high enough concentration, POE tallowamine itself did have toxic properties in the case of certain organisms, he said.

Concern usually revolved around the stability and durability of herbicides and pesticides after being dispersed in the environment. If their stability was high and they remained on edible produce for far too long, it meant they could be consumed together with the vegetables containing them. There were also concerns about their solubility in water, as rainwater would be able to take chemicals down to the water table or nearby seawater.

On the other hand, chemicals that were not easily soluble in water were normally quite soluble in fatty matter, meaning they could be absorbed through the skin if contaminated harvested produce came in contact with animals or people.

killed by public funds

The price the ecosystem pays to have ‘cheap food. Is it worth it?

Prof. Vella acknowledged there was concern about pesticides and herbicides in general, however, he advised on looking at both sides of the coin. The use of pesticides allowed agriculture to produce food in much larger volumes and cheaper prices than without the chemicals.

While it was possible to live in a pesticide-free environment, society would likely have to pay a price. Apart from increased cost of foods, the decline in production could cut off some people’s access to meat, fruit and vegetables and that would also have health consequences, Prof. Vella pointed out.

______________________________________________________

Does the EU authorise the placing on the market of pesticides?

dead bee 8

who is paying for this if we may ask?

No, that’s the role of member states but active substances in the pesticides have to be approved at EU level. Once an active substance is approved at EU level, the safety evaluation of every pesticide formulation is done at a later stage by individual member states before they grant, refuse or restrict the use of pesticides formulations at national level.

In their authorisation decision, member states can therefore define the conditions for use of the product, for instance, restricted to certain crops, for professional use or for use in glass houses only.

*Information taken from the European Commission site.

______________________________________________________

 

further reading:

https://alfredbaldacchino.wordpress.com/2017/01/05/sena-dizastru-ghan-nahal/

https://alfredbaldacchino.wordpress.com/2016/03/29/glyphosate-debate-goes-on/

https://alfredbaldacchino.wordpress.com/glyphosate-debate-goes-on-2/

https://alfredbaldacchino.wordpress.com/2015/05/11/il-bexx-kimiku-is-sahha-tal-bniedem-u-tal-ambjent-1/

https://alfredbaldacchino.wordpress.com/2015/05/11/il-bexx-kimiku-is-sahha-tal-bniedem-u-tal-ambjent-2/

https://alfredbaldacchino.wordpress.com/2013/08/17/bees-alert-its-goodbye-honey/


Tunnelling the cross

May 24, 2016

times of malta

Tuesday, 24th May, 2016

Tunnelling the cross

Alfred E. Baldacchino

The proposed tunnel crossing under the 10km Gozo Channel seems to have surfaced again. Those in favour of this tunnel are putting forward every thinkable reason to justify such a tunnel. Such justifications include the long waiting queues on both sides of the channel, the Gozo aging population, the lack of job oppportuity in Gozo, and also that residents do not want to rely on touristic income to live in Gozo.

2016.05.24 - tunnelling the cross

Photo: viewingmalta.com from The Times

One Gozitan businessman also said that the tunnel would be just another road as the one leading from Marsascala to Valletta. Furthermore, it was also said that the present ferries will be obsolete within 15 years time.

A feasibility study concluded in favour of the tunnel. Externalites, that is the hidden costs that society and the environmenet will have to pay, were not even mentioned, despite the fact that it was concluded that profits in millions would be achieved. Geological studies have not even been initiated. It seems that these are not important as long as it has been concluded that there would be a financial profit.

The geologist Dr Peter Gatt, has pointed out that the area is full of large and deep faults. He also added that it is not only difficult to tunnel through these unstudied faults, but this can also be dangerous to human life.

The maximum depth of water in the channel is estimated to be 30 metres. Excavation depth in the rock bottom, without the availability of geological studies, is estimated to be 70 metres, that is 100 metres below sea level. The openings of this undeground tunnel can lead to the Nadur lowlands on Gozo and Għadira on the mainland.

A number of questions not only have not been answered, but have not even been asked, such as:

How will the tunnel affect both islands from a social and environmental point of view?

Have studies, if any, shown the impact of excavations at the two ends of the tunnel, on the hydrology and agriculture of the areas?

How will the estimated meagre one to two million cubic metres of excavated material be disposed of, and what will be its social and ecological impacts?

How will the tunnel contribute to curb the Gozitan ageing population? Will it instead contribute to further increase it?

Have any studies been done to see if the tunnel will further attract Gozitan youths to spend the weekend on the mainland for entertaining purposes and thus contributing to further add to the exodus from Gozo?

How will the tunnel affect internal tourism? I remember that in the recent past, when there was the ferry service available after the operettas held in Gozo, the commercial entities complained because this affected the bed nights in Gozo because theater visitors could easily return home after the performance. The tunnel would make this possible 356 days a year.

How would the tunnel impact the number of bed nights taken by foreign tourists in Gozo?

A fast ferry service would be the best sustainable solution from a social, environmental and even economic point of view

Initial construction costs of the tunnel are estimated at €300 million, which can easily double, depending on the geological studies. What would be the additional cost with respect to maintenance, and other requisites, for the safety of commuters: for example extraction and injection of fresh air through the tunnel? And how would these increase the toll that commuters will have to pay to cross through the tunnel?

These financial, social and environmental expenses, with the added externalities, are needed for crossing just a 10km stretch of water, not taking into consideration other construction problems. One has also to keep in mind any arising problems during its running, such as traffic accidents or other unforeseen circumstances.

The traffic problems on both sides of the tunnel will not only remain the same as they are today, but there is the probability that these will be further accentuated. Unless of course additional millions are pumped in with further social and environmental hidden costs.

Without doubt, the present facilities to cross the channel are anything but customer friendly. BUT, the tunnel is not the sustainable solution.

The present ferry service contributes to a substantial part of the problem.

It has no competition at all to render it more friendly and adjusted to commuters’ requests and demands. It is a monopolistic service.

Such is the monopolistic management that if there is somebody who believes that he is more important than all the commuters waiting at both quays, he can call back the ferry which has just departed to accommodate him!

The waiting commuters can wait a little longer, be they workers, students, tourists or just common citizens. And the expenses incurred to build such a sustainable tunnel are not the way to control such a monopolistic service.

The ferries in use today were launched in the early 2000. During that time the demand was not as heavy as it is today. Following intensive, successful advertisements to visit Gozo, the demand increased by leaps and bounds, reaching the million mark today. But the number of ferries remained as it was originally, resulting in occasional delays and long queues. If the service were run on competitive lines, without any doubt the problem would not be so acute.

It is quite a relief to hear that a fast ferry service is an alternative to the tunnel. This fast service, besides shortening the time of crossing, can also take commuters, car and all, from Mġarr not only to Ċirkewwa, but also to Valletta, Sliema and any other planned destination on the mainland. This can be enhanced by the availablility of a shuttle bus service from the quay to various bus terminuses.

Such a fast ferry service would be the best sustainable solution from a social, environmental and even economic point of view. Not only so, but it can be faster for commuters, it will avoid time in traffic bottlenecks, it will ease the stress of commuters, it will contribute to the decrease of vehicular emissions, it can also be cheaper and daily commuters can leave their cars on the quay close to home. The tunnel does not address these benefits.

Obviously such a fast ferry service cannot be afforded monopolistic protection, or the problems will still persist.

Speakers, both Gozitans, for the two main parties are leading the front in favour of the tunnel. Only Alternattiva Demokratika is against. One of the former said that all Gozitans are in favour of the tunnel: the vociferous ones that is, but I do not believe that the silent majority are.

The other politician, from the other side of the fence, said that this is a Gozitan project which will benefit Gozitans, and that both parties will include it in their electoral manifesto. Does this mean that those who are against such a tunnel should not vote for the parties who are in favour? A Gozitan friend of mine who is against the tunnel, after hearing such comments on the air, told me that both parties have lost his vote.

The present tunnel vision is more like walking blindfolded searching for a presumed lost black cat in a dark tunnel, to the background music of counting machines.

aebaldacchino@gmail.com

Further reading:

https://alfredbaldacchino.wordpress.com/2014/08/01/efficient-link-to-gozo/


Where the wind blows

April 12, 2016

times of malta

Tuesday, April 12, 2016

Where the wind blows

Alfred E. Baldacchino

The EU met on 8th March 2016 to decide whether to extend for another 15 years, the use of glyphosate, a crucial weedkiller ingredient. The decision was abruptly postponed at the eleventh hour.

pic-3

A glyphosate-based weed killer

Glyphosate is a non-selective herbicide that is widely used in agriculture, public areas and private gardens. It is also used in genetically modified crops, which are specifically engineered to resist glyphosate-based products.

The International Agency for Research on Cancer (IARC), part of the World Health Organisation, announced that glyphosate was “probably carcinogenic to humans”.  Environmental groups have since been calling for its ban.

Following WHO’s warnings, the European Chemicals Agency (ECHA) will undertake further studies to see if glyphosate can cause cancer, interfere with reproduction or damage the hormone system. The herbicide glyphosate can enter the body through food or drinking water. A new study has shown that the majority of Germans have been contaminated by the compound.

killed by public funds

Dead pollinators – bees – after spraying pesticides, especially for purely commercial purposes. 

According to scientists, heavy and repeated uses of glypohosate-based herbicides, contributes to many envirionmental and soil-ecosystem problems. Glyphosate results in the greatest public and worker exposure, either directly or through residues in food. And its impacts on biodiversity is also well known: it decimates and eliminates pollinators such as bees.

On the other hand, the European Food Safety Authority (EFSA) contends that glyphosate was unlikely to cause cancer in humans and proposed higher limits on the amount of residue of the weed killer deemed safe for humans to consume, a report which Greenpeace has referred to as “a whitewash”.

spraying pesticides 1

Whose responsibility is it: Ministry of Landscaping? Ministry of Health? Ministry of Environment? Ministry of Consumer Affairs?Ministry for Local Councils? 

The Swedish Environment Minister said: “We won’t take risks with glyphosate and we don’t think that the analysis done so far is good enough. We will propose that no decision is taken until further analysis has been done and the EFSA scientists have been more transparent about their considerations.”

Before the scheduled vote of 8 March, leaders from Italy joined Sweden, France, and the Netherlands against the widely-used herbicide.

Following such postponement, EU Member States were given till the 18 March 2016 to provide their opinion for the next meeting, scheduled for 18 May. But the Times of Malta (March 29) quoted a spokeswoman for the Ministry for Environment, that Malta did not submit such opinion by the 18 March, because discussions were still ongoing.

spraying pesticides 2

Workers are just a cog in the pro-business machine. As long as they deliver, it is not important to ensure that they wear hazardous clothing.

Following a number of articles and comments in the press, it is now more than obvious that in Malta the eagerness for monitoring and enforcing is at its lowest ebb, if at all. The professionalism of passing the buck is more pronounced.

As per Pesticides Control Act, 2001 and the Malta Competition and Consumer Affairs Authority Act, 2011, the competent authority for the authorisation and regulation of pesticides in Malta is the Malta Competition and Consumer Affairs Authority (MCCAA).

But, according to this newspaper, MCCAA refused to state it’s position and directed questions to the Environment Ministry. The latter is responsible for the protection of biodiversity, the Pesticides Control Board (PCB) which is chaired by a Ministry’s representative, and also for agriculture for which a parliamentary secretary is accountable.

Because of the impacts of pesticides on human food and animal feeds, representatives of the Food and Safety Commission and the Environment Health Department, both under the responsibility of the Minister for Energy and Health are represented on the PCB.

“I tend to start believing that Malta will not go to the next meeting on May 18 with an official public position”

One of the functions of the Food and Safety Commission is to effectively apply the precautionary principle when a significant risk to consumers is identified or reasonably suspected. Sitting on the fence is the Minister of Landscaping who is responsible for use of pesticides by his landscaping official public partner who seems to be immune to any regulation with regards to human safety and biodiversity.

One would tend to ask. “What would Malta have voted if the matter was not postponed?” In such a sensitive social and ecological matter, one would have thought that the decision was easy. But in all probabilities the pro-business vision is quite a high and a strong hurdle to overcome.

From past and present experience, considering the pro-business vision dominating every other sector, and the fortunate position in the EU’s alphabetical list, I tend to start believing that Malta will not go to the next meeting on 18 May with an official public position. The position will be reached according to the way the majority of the EU Member States vote: in other words, where the wind blows.

spraying pesticides 3

Commercial interests spray to their heart’s content: in public area, in public gardens, in street, outsides residential areas, close to public outlets. Anywhere as long as they make some profit out of it. Externalities will be paid by the general public and the environment. 

This despite the negative impacts that such a decision will undoubtedly have on society and ecology, which will be more acute locally considering the smallness of the country. Why does Malta have to be feel embarrassed by a vote in favour of society and the environment?

Miriam Dalli, member of the European Parliament Environment Committee, is quoted as saying that “ultimately we are speaking about the health of our citizens and this is another case where I stand firm in my belief that public health is not negotiable and must not be compromised by any commercial interest.”

One has to wait till the vote on 18 May to see what stand Malta will take: whether MCCAA will be on the side of commercial interests, or use the precautionary principle in the interests of social and environmental health.

aebaldacchino@gmail.com

related articles

https://alfredbaldacchino.wordpress.com/2016/03/29/glyphosate-debate-goes-on/https://alfredbaldacchino.wordpress.com/glyphosate-debate-goes-on-2/

 


It never rains, it pours

March 26, 2016

times of malta

Saturday, 26th March 2016

It never rains, it pours
Alfred E. Baldacchino

The lack of rain this winter has become a great concern for many social leaders. Parched valleys, dried cisterns, empty wells, wilted vegetation, worried farmers, are just a harbinger of things to come during the coming hottest months of the year. This acute drought is making some leaders, whether political or religious, feel a little bit wet under the collar.

Seemingly as a last resort, I would say more for convenience sake to appease their faithful, these social leaders are either reverting to PR exercises instead of working on the long overdue water management plans, or praying the Creator, asking Him for His intervention to send us some of the much needed rain. What an embarrassment!

TOM photo

Efforts were made to catch every drop and save it as a priceless resource without the help of any financial institution. Photo: Chris Sant Fournier – Times of Malta.

The Lord has always given us rain water for free during the years. He has also given us intelligence. One can see the results of such intelligence in past engineering works with regards to water harvesting. One can find and see the professional management of such a rare natural resource dating back to the times before Christ. Efforts were made to catch every drop and save it as a priceless resource without the help of any financial institution. In fact the

bell shaped water cistern in Valletta photo Keith Buhagiar

bell shaped water cistern in Valletta. photo Keith Buhagiar

Maltese islands are dotted with historical professional engineering projects with the sole aim that not a drop of water is wasted. This has seen the population of these islands go through two world wars without having any problems with water, which the Lord sends us for free.

But in the last 50 years, when we took over the management of our Country, we became affluent, like affluent rats, and we boast about it. This has led us to put a price to everything, and discard natural resources which are given to us for free. We are convinced that we have complete control over the ecosystem. Free assets, such as water, are regarded as having no commercial, economic, social or environmental value, and these can be exploited whenever and however we want to.

Today we live for the day, and exploit everything that we lay our eyes and hands on. Mainly, with endemic political intelligence, we ruined, and are still in the process of doing, whole historical engineering networks which contribute to the storing of such a rare natural resource.

LN-376-of-2012

How the professional management of water was adulterated for political reasons

page-1

Professional legislation with regards to the management and conservation of water was adulterated, to accommodate speculators, with an eye on votes. We lost sight of this natural resource to the extent that official entities, like MEPA, that notorious environmental watchdog, prefers planning to store cars instead of planning to catch and store every drop of the rare resource of free rain water.

In our desperate greed, we contributed to the flooding of inhabited areas where the relatively poor reside, besides neglecting the water table with regards to its replenishment, its conservation, its abuse, and the enforcement of legal protection.

But the endemic political acumen, came out with a solution. This led to the asking for help from the new milking cow. Approximately €57 million were used to dig an underground tunnel so that all the free rain water which we are gifted with, could be swept to the sea. Such a scenario emerged from the uncontrolled development and lack of planning as a result of which water could not seep into the aquifer. A pain in the neck when rain water floods our street because of such mismanagement.

If we made use of the intelligence the Almighty gave us, as our ancestors did, we would have restored all the historic cisterns and wells, build new ones to capture and collect all the water, and not ask school children to catch a drop, and throw millions of gallons out to sea. Imagine if the historic professional water management systems were appreciated, cared for, renovated and kept in a good shape. There would not be any reason to pray for rain. Imagine if large cisterns were built in all the school yards, of which there are so many.

Wouldn’t the €57 million have been well spent and such harvested natural resource be so beneficial in this time of drought? But such common sense was not so common with the planning authority, or else these were regarded as whitebait not palatable and attractive enough to the sharks!

2012.10.00 - works in progress while the appeal keeps being postponed

The cemetery built in Nadur Gozo, disrupted and ruined the natural hydrological system and the professional engineering built by the Knights of Malta.

The religious authorities did not bat an eyelid for such waste of resources either. Not only so, but some had also a finger in the pie in the mismanagement of such a natural scarce resource. With MEPA’s blessing, they chose the largest water catchment area in Gozo where to build a cemetery. Yes, a cemetery consisting of 600 graves for the dead at the expense of the living. An appropriate adequate grave for present day intelligence.

In the process, a historical engineering system, which was used to catch free rain water and harvest it in various cisterns, was ruined. This system used to ensure enough adequate water for agricultural needs of the farmers along Wied il-Qasab during the long hot summer months. But because of such mismanagement and lack of professional planning, today when it rains, not only is the water not collected for agricultural use, it now floods the fields further down the valley. The result of the approved plans, by you know who, which interfered with the flow of water through the geological strata. And the cemetery was blessed too!

eco-1This is why I feel embarrassed to pray for rain. I am surprised at the audacity some have, especially those who believe that they are closer to the Lord than any other. Why should the Lord listen to us when a great percentage of such free rain water would be swept to the sea as unwanted, undesired and useless water. And it also floods agricultural land because of land mismanagement and land abuse. What an embarrassment to man’s intelligence. How shameful!

And in the meantime, despite such a drought, large expanses of turf are still being sprinkled (during the darkness of night) with the Minister for Landscaping’s blessings.

If I had to pen a tentative reply to such prayers, I would say: “Be blessed, go and repent.” And remember that “Water is the driving force of all nature” (Leonardo da Vinci).

aebaldacchino@gmail.com

Additional reading:

https://alfredbaldacchino.wordpress.com/2016/02/29/dezert-niexef-nixfa-ta-ideat/

https://alfredbaldacchino.wordpress.com/2016/02/29/l-immaniggar-tal-ilma-fmalta/

https://alfredbaldacchino.wordpress.com/2016/02/14/in-nixfa-tax-xitwa-u-s-sigra-tal-lewz/

 https://alfredbaldacchino.wordpress.com/2010/06/21/the-nadur-cemetery-%e2%80%93-where-the-dead-will-haunt-and-curse-the-living/

https://alfredbaldacchino.wordpress.com/2011/07/04/an-official-water-policy/


A splitting image of Mepa

August 3, 2015

times of malta

Monday, 3rd August, 2015

A splitting image of MEPA 

Alfred E Baldacchino

mepa logo-1

MEPA’s failure in its environmental responsibility started from day one. Barely a week from the ‘merger’ with the Environment Department, in 2001, I was told in a joking vein: “forget about environment; it is development which dictates here.”

And so it was to be. And so it is today. Honouring national and international environmental obligations, which were never understood or wanted to be understood by MEPA, seemed like trying to swim up the Niagara falls. Eventually, environment became MEPA’s Cinderella, leading to its present headless mummified state in limbo.

After two years in government, it has now been thought appropriate to resuscitate such a mummy. Despite being an electoral promise, the move is accompanied by a lot of fanfare and publicity, and this raises more questions than answers. Is it to hide past failures and the procrastination in making such move? Is it to detract from the fact that environment has been kept out of the portfolio of the Minster for the Environment but is in that of the Prime Minster? Is it to make up for the environmental degradation which also saw the Environment Directorate degenerate into a mummified orphaned headless Cinderella? Is it just meant for that part of the electorate who can be convinced that a circle is square?

To consolidate MEPA complete disregard for the environment, on its death bed MEPA, forwarded a report to the Prime Minister, a couple of weeks ago, suggesting that Żonqor was the best site for the university development. The report completely ignored the Environment Directorate, it’s acting Director (no Director since change of government) and the MEPA board too.

MEPA has stooped so low, with such farcical unprofessional behaviour along the years, that it has lost all credibility. It is in need of new image to “secure better planning”!  Is the colourful publicity and change of name merely dressing the old wolf in new sheep’s clothing? Many already see the Executive Council referred to in the new Bills, as already set up and running, as evidenced by the Żonqor report. It seems that the rape will go on, till there is nothing left to rape.

As advertised, MEPA will be no more, and will only be remembered in the books of history especially for its complete environmental failures. Few would shed a tear.

 

trophy

Future generations have a right to know who was responsible for the protection of the Maltese environment, which they have lent us.

I won’t. I have gone through the new environment bill. An exercise undertaken by a parliamentary secretary in the office of the prime minister. The new bill transposes all the environmental provisions from the MEPA Act (except for some ‘overlooked touches’): a cut and paste exercise to ensure that the EU Environment Aquis obligations are all there.

If the new Environment Act is to put the environment high on the agenda, why was it not possible to achieve such aims, with the same legal provisions, when it was under the responsibility of the Prime Minister? Is all this fanfare a confirmation of failure? MEPA has been declared a monster, without any political control, when as everybody knows it functions by political nods, as one concludes from a rationalised  żonqor point.

I honestly believe that the Minster for the Environment, Leo Brincat, can administer the environment on professional lines. Perhaps this is why he has been kept away from environmental responsibility, and MEPA, environment and all, are still not in his portfolio after two years. It is nice to have someone to shield the blows though!

One now hopes the Minster for the environment won’t be given a ‘promotion’ and be replaced by someone whose main qualification will be to convince us that he is ‘balancing’ environment and planning, naturally in the ‘national’ interest. This would only result in handing over of a mummified headless Cinderella from limbo, nicely adorned as a skeleton on a string, controlled by the Executive Council.

 

 

cartoon

What trust can one have in the headless skeleton, resuscitated and dressed as an Environmental Authority? In the absence of such trust, which is not easy to re-establish, it is very difficult to believe everything that is being said.

Those who yearn for a better future, better social wellbeing, a better environmental home, have to fasten their seatbelts. We are all in for a rough ride.

I sincerely wish all the good luck to the Environment Minister who will need all the help he can from genuine individuals and social entities, especially from the political field.

Unfortunately though he will have a lot of bones to pick with.

——————————————

PS – graphics were added to the original article.